bathroom remodel
May. 1st, 2016 11:20 pmMonday: Demolition
Tuesday: Demolition. It didn't take all day.
Wednesday: rough framing. This consisted of new subfloor, and a few new studs in the wall. I'm sure it took about half the day.
Thursday: rough plumbing.
Friday: I told the electrician what we want.
Tomorrow will be the rough electrical work,
Tuesday will be inspection, then insulation and vapor barrier followed by another inspection. I think the inspector only works tuesdays, which is why I'm not concerned that no work was done on friday.
If it was the same guys doing all the work, they could have easily gotten all that done in about four days instead of six.
Tuesday: Demolition. It didn't take all day.
Wednesday: rough framing. This consisted of new subfloor, and a few new studs in the wall. I'm sure it took about half the day.
Thursday: rough plumbing.
Friday: I told the electrician what we want.
Tomorrow will be the rough electrical work,
Tuesday will be inspection, then insulation and vapor barrier followed by another inspection. I think the inspector only works tuesdays, which is why I'm not concerned that no work was done on friday.
If it was the same guys doing all the work, they could have easily gotten all that done in about four days instead of six.